Addison Creek Improvement Fall 2024 Update
Fri September 20, 2024
Update as of 09/12/2024
Westchester from Gardner Road to Roosevelt Road
- Construction began January 2024 and will continue through April of 2025
- Tree clearing complete
- Drilled shaft installation and retaining wall construction ongoing through September of 2024
- Excavation and gabion installation to occur Septeber through December 2024
- Pavement restoration on east side of creek to occur October 2024.
- Pavement restoration on weide of creek to occur April 2025
This information was provided by the Metropolitan Water Reclamation District news section on their public information website. Please visit their page for the most current information.